Question: Analyze the five proposals and make recommendations based on expected costs. MINI CASE The Sharon Construction Corporation has been awarded a contract for the construction
Analyze the five proposals and make recommendations based on expected costs.
MINI CASE
The Sharon Construction Corporation has been awarded a contract for the construction of a 20,000-seat stadium. The construction must start by February 15 and be completed within one year. A penalty clause of $15,000 per week of delay beyond February 15 of next year is written into the contract. Jim Brown, the president of the company, called a planning meeting. In the meeting he expressed great satisfaction at obtaining the contract and revealed that the company could net as much as $300,000 on the project. He was confident that the project could be completed on time with an allowance made for the usual delays anticipated in such a large project. Bonnie Green, the director of personnel, agreed that in a normal year only slight delays might develop due to a shortage of labor. However, she reminded the president that for such a large project, the company would have to use unionized employees and that the construction industry labor agreements were to expire on November 30. Past experience indicated a fifty
Step by Step Solution
3.41 Rating (164 Votes )
There are 3 Steps involved in it
The first element necessary to analyze this situation is a project schedule for the base plan The Gantt chart from Microsoft Project for the plan without any alterations looks like this The following ... View full answer
Get step-by-step solutions from verified subject matter experts