Question: Apply critical-chain scheduling principles to the Print Software, Inc., project presented in Chapter 6. Revise the estimated time durations by 50 percent except round up
.png)
Figure (a) Air Control Project CCPM Network Order endor parts FB std. parts Mfgr. cust. parts iTest Order FB FB cust. parts Task Software 10 Figure (b) Air Control Project Gantt Chart: CCPM Activity DUR LS LF Buffer 1. Order review 2.Order vendor parts 8 7 15 3. Produce std. parts8 4. Design cust. parts 5. Software dev. 6. Migr. cust. parts 7. Assemble 8. Test 9 10 1 21 8 1119 6 18 24 324 27 12 0 5 10 15 20 25 30 35 40 ActivityBufer
Step by Step Solution
3.43 Rating (172 Votes )
There are 3 Steps involved in it
Below is the CCPM network drawn for the Printer Software project Next is the CCPM Ga... View full answer