Question: Assume that your class instructor appointed you project manager to lead a dozen of your classmates in writing up the end-of-chapter pedagogy materials. You plan
Assume that your class instructor appointed you project manager to lead a dozen of your classmates in writing up the end-of-chapter pedagogy materials. You plan to form subteams to work on each of these elements, each headed by a subteam leader. Of course, all the subteam materials will need to be integrated into the final Instructor’s Guide at the end. Construct a WBS and RACI Matrix for this project.
Step by Step Solution
3.48 Rating (165 Votes )
There are 3 Steps involved in it
The WBS for this project might be as follows Review Questions ... View full answer