Question: Assume that your project team has been working for three months to complete the systems design of a new Web-based customer ordering system. Two possible
.png)
a. What process would you follow to make this important decision?
b. Who needs to be involved?
c. What additional questions need to be answered to make a good decision?
d. Based on the data, which option would you recommend and why?
e. How would you account for project risk in your decisionmaking?
Factor Annual gross savings Total development cost Annual operating cost Time required to implement Risk associated with project Option 1 Option 2 $1.5 million $3.0 million $1.5 million $2.2 million $0.5 million $1.0 million 9 months 15 months (expressed in probabilities) Benefits will be 50% less 20% 35% than expected Cost will be 50% greater 25% 30% than expected Organization will not/cannot 20% 25% make changes necessary for system to operate as expected Does system meet all Yes es mandatory requirements?
Step by Step Solution
3.36 Rating (162 Votes )
There are 3 Steps involved in it
The following comments provide direction for this team activity a A costbenefit analysis should be c... View full answer