Question: Assume you are working on a on a project using lean manufacturing. Now you are preparing your schedule. You feel your tasks may be relatively
Assume you are working on a on a project using lean manufacturing. Now you are preparing your schedule. You feel your tasks may be relatively similar in size and scope. You should consider-
A. Fixed number of work periods B. Percent of the estimated activity duration C. Buffers D. * Kanban system