Question: Assume you are a project cost engineer calculating the cost of a repetitive activity for your project. There are a total of 20 iterations of
Yx = aXb
Where:
Yx = the time required for the steady state, x, unit of output
a = the time required for the initial unit of output
X = the number of units to be produced to reach the steady state
b = the slope of the learning curve, represented as: log decimal learning rate/log 2