Question: At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To

At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days).


At a local university, the Student Commission on Programming and


a. Draw the project network.
b. Compute the expected duration and variance of each activity.
c. Determine the critical path in the project network.
d. What is the expected duration and variance of the critical path?
e. What is the likelihood that the project will be completed within 30 days?
f. If activity B is delayed by six days beyond its early start time, how does this affect the expected projectduration?

Immediate Most Activitv Predecessors) Optimistic Probable Pessimistic A: Negotiate contract with 10 15 selected musicians B: Resetve site C: Manage travel logistics 10 for music group D: Screen & hire security personnel E: Arrange advertising B, C & ticketing F: Hire parking staff G: Arrange concession sales 10 10 4.

Step by Step Solution

3.59 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b Activity Expected Time Variance A 105 136 B 8 011 C 6... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

272-M-S-Q-M (514).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!