roblem markroblem marks At a local university, the Student Commission on Programming and
Entertainment SCOPE is preparing to host its first rock concert of the school year. To
successfully produce this rock concert, SCOPE has listed the requisite activities and related
information in the following table duration estimates measured in days
Activity Immediate
Predecessor
s
Optimistic Most
probable
Pessimistic
A: Negotiate contract with selected
musicians
B: Reserve site
C: Manage travel logistics for music
group
A
D: Screen & hire security personnel B
E: Arrange advertising & ticketing BC
F: Hire parking staff D
G: Arrange concession sales E
a marks Draw the project network, indicating the earliest start, earliest finish, latest start,
and latest finish day of each activity.
b marks What is the expected duration and variance of the critical path?s At a local university, the Student Commission on Programming and
Entertainment SCOPE is preparing to host its first rock concert of the school year. To
successfully produce this rock concert, SCOPE has listed the requisite activities and related
information in the following table duration estimates measured in days
Activity Immediate
Predecessor
s
Optimistic Most
probable
Pessimistic
A: Negotiate contract with selected
musicians
B: Reserve site
C: Manage travel logistics for music
group
A
D: Screen & hire security personnel B
E: Arrange advertising & ticketing BC
F: Hire parking staff D
G: Arrange concession sales E
a marks Draw the project network, indicating the earliest start, earliest finish, latest start,
and latest finish day of each activity.
b marks What is the expected duration and variance of the critical path?