At the beginning of the year, Pryor Company estimated the following costs: Overhead.................................$ 900,000 Direct labour cost........................1,200,000
Question:
At the beginning of the year, Pryor Company estimated the following costs:
Overhead.................................$ 900,000
Direct labour cost........................1,200,000
Pryor uses normal costing and applies overhead on the basis of direct labour cost. (Direct labour cost is equal to total direct labour hours worked multiplied by the wage rate.) For the month of December, direct labour cost was $77,800.
Required:
1. Calculate the predetermined overhead rate for the year.
2. Calculate the overhead applied to production in December.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Cornerstones of Managerial Accounting
ISBN: 978-0176530884
2nd Canadian edition
Authors: Maryanne M. Mowen, Don Hanson, Dan L. Heitger, David McConomy, Jeffrey Pittman
Question Posted: