Atro Co. (a U.S. firm) considers a foreign project in which it expects to receive 10 million

Question:

Atro Co. (a U.S. firm) considers a foreign project in which it expects to receive 10 million euros at the end of one year. While it realizes that its receivables are uncertain, it decides to hedge receivables of 10 million euros with a forward contract today. As of today, the spot rate of the euro is $1.20, while the one-year forward rate of the euro is presently $1.24, and the expected spot rate of the euro in one year is $1.19. The initial outlay of this project is $7 million. Atro has a required return of 18%.
a. Estimate the NPV of this project based on the expectation of 10 million euros in receivables.
b. Now estimate the NPV based on the possibility that country risk could cause a reduction in foreign business, such that Atro Co. only receives 4 million euros instead of 10 million euros at the end of one year. Estimate the net present value of the project if this form of country risk occurs.
Net Present Value
What is NPV? The net present value is an important tool for capital budgeting decision to assess that an investment in a project is worthwhile or not? The net present value of a project is calculated before taking up the investment decision at...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: