A&W Manufacturing has implemented an activity-based costing system. For warehousing/packaging, the activity cost totals $140,400. ±he number

Question:

A&W Manufacturing has implemented an activity-based costing system. For warehousing/packaging, the activity cost totals $140,400. ±he number of batches produced is the cost driver for this activity pool. A&W has the following information relating to its warehousing/packaging department
Number Of Batches 300 100 50 450 Units Per Batch Budgeted Production 1,500 300 250 Product A Product B Product C Total 3

Required: Calculate the acTvity cost rate per batch for the warehousing/packaging department.