Question: Balance the assembly line for the tasks contained in the table. The desired output is 240 units per day. Available production time per day is

Balance the assembly line for the tasks contained in the table. The desired output is 240 units per day. Available production time per day is 480 minutes.

Work Time Immediate Predecessor(s) Element (Sec.) 40 45 55 55 65 40 C,D 25 D,E

a) What is the desired Cycle time in seconds?
b) What is the theoretical minimum number of stations?
c) Use trial and error to work out a solution in the table below. Your efficiency should be at least 90%.
d) Calculate the efficiency of your solution.

Work Time Immediate Predecessor(s) Element (Sec.) 40 45 55 55 65 40 C,D 25 D,E

Step by Step Solution

3.52 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Balance the assembly line for the tasks contained in the table The desired output is 240 units per ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

1368-B-M-A-V-C(1576).xlsx

300 KBs Excel File

Students Have Also Explored These Related Managerial Accounting Questions!