Question: Complete the following MPS Record Lot Size 130 Lead Time 1. Quantity on Hand 45 1. 10 Forecast 25 25 25 25 50 50 50
Complete the following MPS Record
.png)
Lot Size 130 Lead Time 1. Quantity on Hand 45 1. 10 Forecast 25 25 25 25 50 50 50 40 20 Customer Orders (booked) 30 Projected On-Hand Inventory MPS Quantity MPS start Available to Promise Inventory 4. 20
Step by Step Solution
3.57 Rating (164 Votes )
There are 3 Steps involved in it
Computation of the following Lot Size 130 Lead Time 1 ... View full answer