Question: Based on your concerns, Jack has gathered the following information for Work Center 2, the work center that directly feeds Work Center 3. Complete the
.png)
(a) Complete the input/output record.
(b) Describe your concerns based on the results of the input/outputanalysis.
Input Information (in hours) 4 5 6 7 8 40 50 50 60 60 25 35 35 40 40 Planned input Actual input Deviation Cumulative deviation Output Information (in hours) Planned output Actual output Deviation Cumulative deviation Backlog 75 hours 40 50 50 60 60 45 45 45 55 60
Step by Step Solution
3.36 Rating (162 Votes )
There are 3 Steps involved in it
a Input Information in hours 4 5 6 7 8 Planned input 40 50 50 60 ... View full answer