Question: Bradford Services Inc. (BSI) is considering a project with a cost of $10 million and an expected life of 3 years. There is a 30%
Bradford Services Inc. (BSI) is considering a project with a cost of $10 million and an expected life of 3 years. There is a 30% probability of good conditions, in which case the project will provide a cash flow of $9 million at the end of each of the next 3 years. There is a 40% probability of medium conditions, in which case the annual cash flows will be $4 million, and there is a 30% probability of bad conditions with a cash flow of -$1 million per year. BSI uses a 12% cost of capital to evaluate projects like this.
a. Find the project's expected present value, NPV, and the coefficient of variation of the present value.
b. Now suppose that BSI can abandon the project at the end of the first year by selling it for $6 million. BSI will still receive the Year-1 cash flows, but will receive no cash flows in subsequent years.
c. Now assume that the project cannot be shut down. However, expertise gained by taking it on would lead to an opportunity at the end of Year 3 to undertake a venture that would have the same cost as the original project, and the new project's cash flows would follow whichever branch resulted for the original project. In other words, there would be a second $10 million cost at the end of Year 3 followed by cash flows of either $9 million, $4 million, or -$1 million for the subsequent 3 years. Use decision-tree analysis to estimate the value of the project, including the opportunity to implement the new project at Year 3. Assume that the $10 million cost at Year 3 is known with certainty and should be discounted at the risk free rate of 6%.
d. Now suppose the original project (no abandonment option or additional growth option) could be delayed a year. All the cash flows would remain unchanged, but information obtained during that year would tell the company exactly which set of demand conditions existed. Use decision-tree analysis to estimate the value of the project if it is delayed by 1 year.
e. Go back to part c. Instead of using decision-tree analysis, use the Black-Scholes model to estimate the value of the growth option. The risk-free rate is 6%, and the variance of the project's rate of return is 22%.
Step by Step Solution
3.49 Rating (172 Votes )
There are 3 Steps involved in it
a WACC 12 Condition Probability CF CF x Prob Good 30 9 270 Medium 40 4 160 Bad 30 1 030 Expected CF 400 Time line of Expected CF 0 1 2 3 10 400 400 40... View full answer