Brian Wilson, materials manager at B&L Inc. in Lancaster, Pennsylvania, was considering a proposal from his purchasing

Question:

Brian Wilson, materials manager at B&L Inc. in Lancaster, Pennsylvania, was considering a proposal from his purchasing agent to outsource manufacturing for an outrigger bracket. It was the end of April and Mr. Wilson had to evaluate the proposal and make a decision regarding whether to proceed.

B&L Inc. manufactured trailers for highway transport trucks. The company comprised three divisions: the Trailer, Sandblast & Paint, and Metal Fabricating Divisions. Each division operated as a separate profit center, but manufacturing operations between each were highly integrated. The Metal Fabricating Division produced most of the component parts of the trailers, the Trailer Division performed the assembly operations, and the Sandblast & Paint Division was responsible for completing the sandblasting and final painting operation. B&L manufactured approximately 40 trailers per year, with about two- thirds produced during the period from November to April.

In an effort to reduce costs, the purchasing agent, Alison Beals, who reported to Brian Wilson, solicited quotes from three local companies to supply the outrigger bracket. Mayes Steel Fabricators (Mayes), a current supplier to B&L for other components, offered the lowest bid, with a cost of $ 108.20, FOB B&L. Brian met with the controller, Mike Carr, who provided a breakdown of the manufacturing costs for the outrigger bracket. Looking at the spreadsheet, Mike commented: “These are based on estimates of our costs from this year’s budget. Looking at the material, labor, and overhead costs, I would estimate that the fixed costs for this part are in the area of about 20 percent. Keep in mind that it costs us about $ 75 to place an order with our vendors.” Exhibit 1 provides B&L’s internal cost breakdown and details from the quote from Mayes.


Brian Wilson, materials manager at B&L Inc. in Lancaster, Pennsylvania,


Brian expected that B&L would have to arrange for extra storage space if he decided to outsource the outrigger bracket to Mayes, who had quoted delivery lead time of four weeks. Because Mayes was local and had a good track record, Brian didn’t expect the need to carry much safety stock, but the order quantity issue still needed to be resolved. B&L was operating in a competitive environment and Brian had been asked by the division general manager to look for opportunities to reduce costs. As he sat down to review the information, Brian knew that he should make a decision quickly if it was possible to cut costs by outsourcing the outrigger bracket.
Analyze the information and make arecommendation.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0078024108

12th edition

Authors: William J Stevenson

Question Posted: