Builder Bug Company allocates overhead at $9 per direct labor hour. Job A 45 required 5 boxes

Question:

Builder Bug Company allocates overhead at $9 per direct labor hour. Job A 45 required 5 boxes of direct materials at a cost of $ 30 per box and took employees 12 hours to complete. Employees earn $ 15 per hour. Compute the total cost of job A 45.