A building contractor obtained bids for some asphalt paving, based on a specification. Three paving subcontractors quoted

Question:

A building contractor obtained bids for some asphalt paving, based on a specification. Three paving subcontractors quoted the following prices and ten of payment:


The building contractor uses a 12% no min interest rate, compounded monthly, in this type c bid analysis. Which paving subcontractor should b awarded the paving job?

Paving Co. Quick Payment Schedule 50% payable immediate 25% payable in 6 month 25% payable at the end of one year Payabl