Question: An engineer has received two bids for an elevator to be installed in a new building. The bids, plus his evaluation of the elevators, are
An engineer has received two bids for an elevator to be installed in a new building. The bids, plus his evaluation of the elevators, are shown in Table P5-69. The engineer will make a present worth analysis using a 10% interest rate. Prepare the analysis and determine which bid should be accepted.
Engineer's Estimates Bids: Installed Cost Annual Operating Cost, Including Repairs Salvage Value at End Service Life (years) of Service Life Alternatives 10 IS Westinghome $45.000 $3000 4500 S2700/yr Itis 2850/yr 54,000
Step by Step Solution
3.34 Rating (166 Votes )
There are 3 Steps involved in it
PW of Cost of 30 years of Westing home 45000 2700 AP 10 30 42000 PF 10 10 42000 PF ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)