Question: Central Iowa Builders Inc. entered into a contract to construct an office building and plaza at a contract price of $10,000,000. Income is to be

Central Iowa Builders Inc. entered into a contract to construct an office building and plaza at a contract price of $10,000,000. Income is to be reported using the percentage-of-completion method as determined by estimates made by the architect. The data below summarize the activities on the construction for the years 2007–2009. For the years 2007–2009, what entries are required to record this information, assuming the architect's estimate of the percentage completed is used to determine revenue (proportional costapproach)?

Central Iowa Builders Inc. entered into a contract to construct

Actual Cost Estimated Cost Percentage Completed Project Collections Incurred to Complete Architect's Estimate Blngs on Billings Year 73.200.000 4.300,000 1,550,000 25% 75 100 200 2008 2009 $6,000,000 1,600,000 $3,300,000 $3,100,000 2,700,000 4,200,000 4,500,000 2,200,000

Step by Step Solution

3.52 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

2007 Construction in Progress 3200000 Materials Labor Cash etc 3200000 Accounts Receivable 3300000 P... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

105-B-A-R-R (307).docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!