Chase Company's production budget is as follows: Budgeted sales in units............................................300,000 Desired units in inventory, December 31.........................70,000
Question:
Chase Company's production budget is as follows:
Budgeted sales in units............................................300,000
Desired units in inventory, December 31.........................70,000
.........................................................................370,000
Estimated units in inventory, January 1..........................50,000
Budgeted units of production. .................................320,000
Each unit takes 30 minutes to produce and the standard labor rate is $18 per labor hour. What is Chase's direct labor budget?
a. $2,880,000
b. $2,700,000
c. $10,800,000
d. $5,760,000