Question: Company has decided to develop cost formulas for its major over- head activities. Wheeler uses a highly automated manufacturing process, and power costs are a
.png)
Required:
1. Prepare a scattergraph by plotting power costs against machine hours. Does the scatter-graph show a linear relationship between machine hours and power cost?
2. Using the high and low points, compute a power cost formula.
3. Use the method of least squares to compute a power cost formula. Evaluate the coefficient of determination.
4. Rerun the regression and drop the point (20,000; $26,000) as an outlier. Compare the results from this regression to those for the regression in Requirement 3. Which is better?
Quarter Machine Hours Power Cost 20,000 25,000 30,000 22,000 21,000 18,000 24,000 28,000 $26,000 38,000 42,500 35,000 34,000 31,400 36,000 42,000 4
Step by Step Solution
3.36 Rating (162 Votes )
There are 3 Steps involved in it
1 Scattergraph Yes the relationship between machine hours and power cost appears to be linear However the observation for quarter 1 may be an outlier ... View full answer