Question: Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders. Release orders in periods 1

Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders.
LLC: 0 Item: X Period LT: 2 Lot Size: Min 50 Gross Requirements 25 30 56 25 100 40 30 20 Scheduled Receipts 50 Projected

Release orders in periods 1 through 5 for quantities of 50, 50, 56, 50, and 50 respectively. Please include/show work on how problem was solved.

LLC: 0 Item: X Period LT: 2 Lot Size: Min 50 Gross Requirements 25 30 56 25 100 40 30 20 Scheduled Receipts 50 Projected on Hand 30 Net Requirements Planned Order Receipts Planned Order Releases

Step by Step Solution

3.44 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Item X Lot Size Min 50 Gross Requirements Scheduled Receipts Proje... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-F-D-F(1455).docx

120 KBs Word File

Students Have Also Explored These Related Corporate Finance Questions!