Complete the following MRP matrix for item A: ITEM: A LOT SIZE: MULT 50 LT: 2 1

Question:

Complete the following MRP matrix for item A:
ITEM: A LOT SIZE: MULT 50 LT: 2 1 2 3 4 5 6 7 8 LLC: 1 PERIOD Gross Requirements 10 15 25 75 60 85 45 60 Scheduled Recei