Question: Consider the following network for a small maintenance project (all times are in days; network proceeds from node 1 to node 7): a. Draw an

Consider the following network for a small maintenance project (all times are in days; network proceeds from node 1 to node 7):

a. Draw an arrow diagram representing the project.

b. What is the critical path and associated time?


Consider the following network for a small maintenance project (


c. What is the total slack time in the network?
d. What is the expected time for 68, 95, and 99 percent completion limits?
e. If activity G had an estimated time of fifteen days, what impact would this have on your answer to partb?

255323950230 366434564344 144212746126 ina od 243644567577 111223344456 JA ! ABCDEFGHIJKL

Step by Step Solution

3.47 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b c d Limit Range Outer Limit 1 68 23 145 2445 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

93-B-M-L-P-M (834).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!