Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes: Given a

Question:

Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes:


Consider the following tasks, times, and predecessors for an assembly


Given a cycle time of four minutes, develop two alternative layouts. Use the longest task time rule and the largest number of following tasks as a secondary criterion. What is the efficiency of your layouts, assuming the 4-minute cycletime?