Question: Consider the project with the listed activities, and precedence relationships. Probabilistic durations are given (represented by Beta-distribution). Times are given in weeks. (a) Compute the

Consider the project with the listed activities, and precedence relationships. Probabilistic durations are given (represented by Beta-distribution). Times are given in weeks.
Expected Durations a Predecessor Variance Activity 5 11 17 B 3 3 3 A 10 15 B 5 3 4 6. 6. 6. B, C 8 E, F 3 8 4. Н 7. 6.

(a) Compute the variance and expected duration of each activity.
(b) Draw an activity-on-node precedence diagram for the project.
(c) Using the most likely time estimates calculates the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), and Slack Time (ST) for the activities in the project.
(d) Identify the critical path.
(e) What is the probability of completing the project in 37 days or less? Use expected durations from part a for calculations.

Expected Durations a Predecessor Variance Activity 5 11 17 B 3 3 3 A 10 15 B 5 3 4 6. 6. 6. B, C 8 E, F 3 8 4. 7. 6. 5. 3. LO

Step by Step Solution

3.35 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Expected time a 4 x m b 6 where a optimistic m most likely and b pessimistic Expected time 5 4 x 1... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-F-D-F(814).docx

120 KBs Word File

Students Have Also Explored These Related Corporate Finance Questions!