Question: A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.

A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks. Activity Precedence Activities Activity Time (weeks) ES LS EF LF Slack Critical Path? A B C D E F G H I Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%?
Start 10 Finish Activity Time (weeks) ES Precedence Critical Activity Activities LS EF LF Slack Path? Н

Start 10 Finish Activity Time (weeks) ES Precedence Critical Activity Activities LS EF LF Slack Path?

Step by Step Solution

3.39 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The probability is less than 50 since 25 weeks is less than t... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-F-D-F(2688).docx

120 KBs Word File

Students Have Also Explored These Related Corporate Finance Questions!