Question: Consider the Reliable Construction Co. project scheduling example presented in Sec. 28.2. Recall that simulation was used to estimate the probability of meeting the deadline
This problem will demonstrate this fact and investigate the impact of the number of trials per simulation on this randomness. The spreadsheet model is available on this website. Make sure that the Monte Carlo sampling method is chosen in Simulation Options.
(a) Set the trials per simulation to 100 in Simulation Options and run the simulation of the project five times. Note the mean completion time and the percentage of trials on which the project is completed within the deadline of 47 weeks for each simulation run.
(b) Repeat part a except set the trials per simulation to 1,000 in Simulation Options.
(c) Compare the results from part a and part b and comment on any differences..
Activity Predecessors
A. Secure funding.......... –
B. Design building.......... A
C. Site preparation.......... A
D. Foundation........... B, C
E. Framing.............. D
F. Electrical............ D
G. Plumbing............ E
H. Walls and roof............ F, G
I. Finish construction.......... H
J. Landscaping........... H
Step by Step Solution
3.40 Rating (172 Votes )
There are 3 Steps involved in it
a A typical set of 5 runs 4583 4626 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
545-M-S-S-M (488).docx
120 KBs Word File