Question: Construct a network diagram for the information in the following table. Use either AOA or AON (see Example 5 for either type). What is the

Construct a network diagram for the information in the following table. Use either AOA or AON (see Example 5 for either type). What is the probability that the project will take more than 10 weeks to complete if the activity means and standard deviations are as shown below? Times are inweeks.
Construct a network diagram for the information in the following

Path Activity Mean Standard Deviation 1.3 1.0 1.6

Step by Step Solution

3.46 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Probability T 10 weeks Path A Expected duration 5 4 9 Standard d... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

372-B-M-L-O-M (3489).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!