Question: Construct the project network for a project with the following activity list. Imnediate Predecessors Estimated Duration Activity 1 month 2 months 4 months 3 months

Construct the project network for a project with the following activity list.
Construct the project network for a project with the following

Imnediate Predecessors Estimated Duration Activity 1 month 2 months 4 months 3 months 2 months 3 months 5 months 1 month 4 months 2 months 3 months 3 months 5 months 4 months D, E G, H