Question: Create a Double Moving Average model (with k = 4) for the data set. a. Prepare a line graph comparing the Double Moving Average predictions
Create a Double Moving Average model (with k = 4) for the data set.
a. Prepare a line graph comparing the Double Moving Average predictions against the original data.
b. What are the forecasts for the next two months using this technique?
Step by Step Solution
3.34 Rating (160 Votes )
There are 3 Steps involved in it
a Moving Dbl Moving Predicted Year t Month Rate Average Average Level Trend Rate 1999 1 1 703 MSE 006758 2 2 708 3 3 762 4 4 793 7415 5 5 807 7675 6 6 832 7985 7 7 825 81425 7804375 848063 022542 8 8 ... View full answer