Question: David Jurman, Ltd., has received the following orders: The entire fabrication for these units is scheduled on one machine. There are 2,250 usable minutes in
.png)
The entire fabrication for these units is scheduled on one machine. There are 2,250 usable minutes in a week, and each unit will take 65 minutes to complete. Develop a capacity plan, using lot splitting, for the 10-week timeperiod.
Period Order size 60 30 10 40 70 10 40 30 40 0 12 34 5 6 7 8 9 10
Step by Step Solution
3.36 Rating (168 Votes )
There are 3 Steps involved in it
David Jurman Capacity Capacity Required Available Over Week Units Time Time Under Production Sc... View full answer