Question: David Jurman, Ltd., has received the following orders: The entire fabrication for these units is scheduled on one machine. There are 2,250 usable minutes in
David Jurman, Ltd., has received the following orders:
.png)
The entire fabrication for these units is scheduled on one machine. There are 2,250 usable minutes in a week, and each unit will take 65 minutes to complete. Develop a capacity plan, using lot splitting, for the 10-week timeperiod.
Period Order size 60 30 10 40 70 10 40 30 40 0 12 34 5 6 7 8 9 10