Question: Define each of these terms, and indicate how each is determined. a. Expected activity time. b. Variance of an activity time. c. Standard deviation of

Define each of these terms, and indicate how each is determined.

a. Expected activity time.

b. Variance of an activity time.

c. Standard deviation of a path’s time.


Step by Step Solution

3.46 Rating (182 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Expected activity time is a weighted average of optimistic mostlikely and pessi... View full answer