Question: Determine the rainfall excess (i.e., runoff) resulting from the 10-yr, 24-hr rainfall for the watershed in Example 11.8. This amounts to completing steps 1, 2,
Determine the rainfall excess (i.e., runoff) resulting from the 10-yr, 24-hr rainfall for the watershed in Example 11.8. This amounts to completing steps 1, 2, and 3 of the design process described in Section 11.6.4 and elaborated in Example 11.6. Albemarle County, in western Virginia, receives 6.0 in. of rain in the 10-yr, 24-hr storm. Use a 2-hr time step.
Step by Step Solution
3.45 Rating (155 Votes )
There are 3 Steps involved in it
The solution procedure follows Example 116 except the P 1 P ... View full answer