Question: Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 6, assuming the cost performance index remains the
Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 6, assuming the cost performance index remains the same through the remainder of the job.
In Problem 6, the actual cost of the work performed at the end of the third week for the project in Problem 4 is $16,500. Determine the cost performance index for the project.
IN PROBLEM 4, A project consists of six tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 4. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 3 and end at the end of Week 4. Task D is scheduled to begin at the start of Week 1 and end at the end of Week 1. Task E is scheduled to begin at the start of Week 2 and end at the end of Week 4. Task F is scheduled to begin at the start of Week 4 and end at the end of Week 4. The budgeted cost for Task A is $10,000, for Task B is $2,000, for Task C is $3,000, for Task D is $1,000, for Task E is $6,000, and for Task F is $4,000. At the end of the third week Task A is 80% complete, Task B is 100% complete, Task C is 40% complete, Task D is 100% complete, Task E is 55% complete, and Task F has not started. What is the schedule performance index for the project at the end of the third week?
Step by Step Solution
3.40 Rating (175 Votes )
There are 3 Steps involved in it
The total estimated cost is 26000 10000 2000 3000 1... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
246-B-F-F-M (1849).docx
120 KBs Word File