Question: Set up a spreadsheet to solve Problem 1. Determine the estimated cost of the work performed each week given the taskswith their associated costs and
Set up a spreadsheet to solve Problem 1.
Determine the estimated cost of the work performed each week given the tasks—with their associated costs and schedules—shown in the following table.
.png)
When a task spans more than one week, the costs should be divided equally among theweeks.
WEEK COST ($) 1,000 4,000 24,000 1,000 8,000 12,000 1,000 1,000 1,000 TASK START FINISH Mobilization Grubbing Rough Excavate Roadway Grade and Roll Sub Grade Place and Compact Road Base Place and Compact Asphalt Grade Shoulders Clean Up Demobilize 4 4 5 6
Step by Step Solution
3.47 Rating (177 Votes )
There are 3 Steps involved in it
Task Cost Start Finish Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Mobilization 1000 Week 1 Week 1 1... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
246-B-F-F-M (1850).xlsx
300 KBs Excel File