Question: Do you understand PERT charts? Refer back to Figure 6-10 and answer the following questions: a. Which activity or activities must be completed before activity
Do you understand PERT charts? Refer back to Figure 6-10 and answer the following questions:
a. Which activity or activities must be completed before activity C can begin?
b. Which activity or activities must be completed before activity G can begin?
c. Which activity or activities must be completed before activity J can begin?
d. What are the five paths through the network? Which one is the critical path?
e. What is the earliest projected start time for activity F?
f. What is the earliest projected start time for activity G?
g. What is the latest time that activity J can begin without delaying the entire project?
h. What is the latest time that activity G can begin without delaying the entire project?
i. What is the slack time for activity G?
Step by Step Solution
3.35 Rating (173 Votes )
There are 3 Steps involved in it
a Only activity B must be completed before activity C can begin b Both activities E and F must be co... View full answer