Question: Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a mergeactivity? ID Description Predecessor Survey site Install
.png)
ID Description Predecessor Survey site Install drainage Install power lines Excavate site Pour foundation None B, C
Step by Step Solution
3.44 Rating (170 Votes )
There are 3 Steps involved in it
Activity A is a burst activity ... View full answer