Question: Draw an earned value chart for the end of the first week (7 days) assuming the time proportionality rule for the project illustrated in the
Draw an earned value chart for the end of the first week (7 days) assuming the time proportionality rule for the project illustrated in the following network diagram given the following costs and percentagecompletions:
.png)
D5 G3 Start B3 E4 H5 Budget, $ Actual, $90 Complete 100 100 100 Activity 300 150 750 450 100 10 50 100 200 100 100 50
Step by Step Solution
3.41 Rating (160 Votes )
There are 3 Steps involved in it
ACTIVITY previous duration budget Actual comp A 0 4 6... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
84-B-M-L-P-M (288).docx
120 KBs Word File
