Question: During 2014 AFCO started a construction job with a contract price of $2,500,000. The job was completed in 2016. The following information is available. Instructions

During 2014 AFCO started a construction job with a contract price of $2,500,000. The job was completed in 2016. The following information is available.


During 2014 AFCO started a construction job with a contract


Instructions
(a) Compute the amount of gross profit to be recognized each year assuming the percentage-of-completion method is used.
(b) Prepare all necessary journal entries for 2015.
(c) Compute the amount of gross profit to be recognized each year assuming the completed-contract method isused.

2014 2015 2016 $600,000 $1,435,000 $2,100,000o Costs incurred to date Estimated costs to complete Billings to date Collections to date 1,400,000 100,000 100,000 615,000 500,000 300,000 2,500,000 2,000,000

Step by Step Solution

3.57 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Gross profit recognized in 2014 2015 2016 Contract price 2500000 2500000 2500000 Costs Costs to da... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

253-B-A-R-R (385).docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!