Question: During 2014 AFCO started a construction job with a contract price of $2,500,000. The job was completed in 2016. The following information is available. Instructions
During 2014 AFCO started a construction job with a contract price of $2,500,000. The job was completed in 2016. The following information is available.
.png)
Instructions
(a) Compute the amount of gross profit to be recognized each year assuming the percentage-of-completion method is used.
(b) Prepare all necessary journal entries for 2015.
(c) Compute the amount of gross profit to be recognized each year assuming the completed-contract method isused.
2014 2015 2016 $600,000 $1,435,000 $2,100,000o Costs incurred to date Estimated costs to complete Billings to date Collections to date 1,400,000 100,000 100,000 615,000 500,000 300,000 2,500,000 2,000,000
Step by Step Solution
3.57 Rating (164 Votes )
There are 3 Steps involved in it
a Gross profit recognized in 2014 2015 2016 Contract price 2500000 2500000 2500000 Costs Costs to da... View full answer