Question: During 2014, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2016. The following information is available.

During 2014, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2016. The following information is available.

2016 2014 2015 Costs incurred to date Estimated costs to complete Billings to date Collections to date $400,000 600,000

Instructions
(a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of completion method is used.
(b) Prepare all necessary journal entries for 2015.
(c) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

2016 2014 2015 Costs incurred to date Estimated costs to complete Billings to date Collections to date $400,000 600,000 300,000 $825,000 $1,070,000 -0- 1,600,000 900,000 1,425,000 810,000

Step by Step Solution

3.38 Rating (176 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Gross profit recognized in 2014 2015 2016 Contract price 1600000 1600000 1600000 Costs Costs ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1407-B-M-A-I(4961).docx

120 KBs Word File