Question: During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available.

During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. The contract is non-cancellable.

During 2017, Nilsen Company started a construction job with a

Instructions:
(a) Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
(b) Prepare all necessary journal entries for 2018.
(c) Calculate the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

2017 2018 2019 S 400,000 S Costs incurred to date Estimated costs to complete Bilings to date (non-refundable) Collections to date 600,000 300,000 270,000 825,000 S 1,070,000 275,000 900,000 810,000 1,600,000 1,425,000

Step by Step Solution

3.27 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Given data 2017 2018 2019 Costs incurred to date 400000 825000 1070000 Estimated costs to complete 6... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

1188-B-C-A-P-C(1167).xlsx

300 KBs Excel File

Students Have Also Explored These Related Cost Accounting Questions!