Question: During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available.
During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. The contract is non-cancellable.
.png)
Instructions:
(a) Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
(b) Prepare all necessary journal entries for 2018.
(c) Calculate the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
2017 2018 2019 S 400,000 S Costs incurred to date Estimated costs to complete Bilings to date (non-refundable) Collections to date 600,000 300,000 270,000 825,000 S 1,070,000 275,000 900,000 810,000 1,600,000 1,425,000
Step by Step Solution
3.27 Rating (156 Votes )
There are 3 Steps involved in it
Given data 2017 2018 2019 Costs incurred to date 400000 825000 1070000 Estimated costs to complete 6... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1188-B-C-A-P-C(1167).xlsx
300 KBs Excel File