Question: Espiritu Construction Co. has used the cost-to-cost percentage-of-completion method of recognizing revenue. Tony Espiritu assumed leadership of the business after the recent death of his
Espiritu Construction Co. has used the cost-to-cost percentage-of-completion method of recognizing revenue. Tony Espiritu assumed leadership of the business after the recent death of his father, Howard. In reviewing the records, Tony finds the following information regarding a recently completed building project for which the total contract was $2,000,000.
2012 2013 2014
Gross profit (loss) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 75,000...$...140,000....$ (20,000)
Cost incurred . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 360,000...............?.....820,000
Espiritu wants to know how effectively the company operated during the last three years on this project and, because the information is not complete, has asked for answers to the following questions.
1. How much cost was incurred in 2013?
2. What percentage of the project was completed by the end of 2013?
3. What was the total estimated gross profit on the project by the end of 2013?
4. What was the estimated cost to complete the project at the end of 2013?
Step by Step Solution
3.44 Rating (173 Votes )
There are 3 Steps involved in it
1 Total gross profit recognized on contract 2012 75000 2013 140000 2014 20000 195000 Total cost incu... View full answer