Question: On June 1, 2013, bids were submitted for a construction project to build a new municipal building and fire station. The lowest bid was $5,000,000,

On June 1, 2013, bids were submitted for a construction project to build a new municipal building and fire station. The lowest bid was $5,000,000, submitted by the Shannon Construction Company. Shannon was awarded the contract. Shannon uses the completed contract method to report gross profit. The following data are given to summarize the activities on this contract for 2013 and 2014. Give the entries to record these transactions using the completed-contract method.

On June 1, 2013, bids were submitted for a construction

Cost Incurred Estimated Cost Billings oCollections of Contract Year to Complete Billings 2013 2014 S1,xD 3,200,000 $2,420,000 2,290,000 0 2,900,000

Step by Step Solution

3.52 Rating (172 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

2013 2014 Construction in Progress 1930000 2290000 Materials Labor ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1121-B-A-C-A-R(3980).docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!