Question: Examine the systems given below. Which system is more reliable, a or b? c or d? Now calculate the reliability of each system. Were your
.png)
If it costs $1000 for each 90% reliable component, $1500 for each 93% component, $2000 for each 95% reliable component, and $10,000 to replace a failed system, which system would you choose, a or b? c ord?
0.93 0.93 (a 0.95 0.950.95 0.90 0.90 90 0.90- 0.90 --0.90 -
Step by Step Solution
3.48 Rating (168 Votes )
There are 3 Steps involved in it
a System A reliability 93 x 93 8649 Component cost 1500 x 2 3000 Failure cost 18... View full answer