Examine the systems given below. Which system is more reliable, a or b? c or d? Now
Question:
If it costs $1000 for each 90% reliable component, $1500 for each 93% component, $2000 for each 95% reliable component, and $10,000 to replace a failed system, which system would you choose, a or b? c ord?