Question: Figure .1 provides a new current state value stream map for the family of retainers at the Jensen Bearings. Inc. firm described in Example 6.1.
Figure .1
.png)
Calculate each component of the new value streams reduced lead time.
a. How many days of raw material does the Bearing's plant now hold?
b. How many days of work in process inventory is held between Press and Pierce &Form?
c. How many days of work in process inventory is held between Pierce &Form and Finish Grind?
020 1 200"S Sheed 500L 200 S 500 5 on
Step by Step Solution
3.31 Rating (145 Votes )
There are 3 Steps involved in it
Calculate daily demand of JB Company It is given that quantity demand for large retainers are 1500 p... View full answer
Get step-by-step solutions from verified subject matter experts