Question: Figure shows a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. b. Four customer orders arrived in the following
Figure shows a partially completed MPS record for ball bearings.
-1.png)
a. Develop the MPS for ball bearings.
b. Four customer orders arrived in the following sequence:
-2.png)
Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should youaccept?
Order Policy 500 units Lead Time: 1 week ltem: Bal bearings Week Quantity 400 2 3 on Hand:400 Forecast 550 | 300 I 400 | 450 | 300 | 350 | 200 | 300 | 450 | 400 Castomer oeders booked) 300 350 250 250 200 150 100 100 100 100 Projected Inventony MPS quantity 500 MPS start Avaitable-to- gromise ATP) inventory Order Quantity Week Desired
Step by Step Solution
3.40 Rating (159 Votes )
There are 3 Steps involved in it
Ball Bearings Prospective MPS a b The first order for 500 in week 4 should be accepted Through week ... View full answer