Question: Florida Power and Light has committed to building a solar power plant. JoAnne, an IE working for VAP, has been tasked with evaluating the three

Florida Power and Light has committed to building a solar power plant. JoAnne, an IE working for VAP, has been tasked with evaluating the three current designs. FPL uses an interest rate of 10% and a 20-year horizon.
Design 1: Flat Solar Panels
A field of flat solar panels angled to best catch the sun will yield 2.6 MW of power and will cost $87million initially with first-year operating costs at $2million, growing $250,000 annually. It will produce electricity worth $6.9 million the first year and will increase by 8% each year thereafter.
Design 2: Mechanized Solar Panels
A field of mechanized solar panels rotates from side to side so that they are always positioned parallel to the suns rays, maximizing the production of electricity. This design will yield 3.1 MW of power and will cost $101 million initially with first-year operating costs at $2.3 million, growing $300,000 annually. It will produce electricity worth $8.8 million the first year and will increase 8% each year thereafter.
Design 3: Solar Collector Field
This design uses a field of mirrors to focus the suns rays onto a boiler mounted in a tower. The boiler then produces steam and generates electricity the same way a coal fired plant operates. This system will yield 3.3 MW of power and will cost $91 million initially with first-year operating costs at $3 million, growing $350,000 annually. It will produce electricity worth $9.7 million the first year and will increase 8% each year thereafter.

Step by Step Solution

3.35 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The design that would be the most economically smart for FPL to build is found out by calculating the net present value of the three current designs Design 1 Flat Solar Panels Year cash outflows Cash ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-A-P-C(836).docx

120 KBs Word File

Students Have Also Explored These Related Cost Accounting Questions!