Question: For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish
For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and slack time. List the critical activities, and determine the expected duration of the project.
a. Problem 1 a.
b. Problem 1 b.
Step by Step Solution
3.35 Rating (164 Votes )
There are 3 Steps involved in it
a Summary Activity ES EF LS LF Slack 12 0 4 7 11 7 13 0 10 0 10 0 24 ... View full answer