Question: For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish

For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and slack time. List the critical activities, and determine the expected duration of the project.

a. Problem 1 a.

b. Problem 1 b.


Step by Step Solution

3.35 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Summary Activity ES EF LS LF Slack 12 0 4 7 11 7 13 0 10 0 10 0 24 ... View full answer